Wednesday, August 26, 2009

Update Week of August 24,09







1, Steel work on the ceiling of the sanctuary level has begun.

2. Jake Walsh, a volunteer from KSC Northern Sangha, has erected the entry posts and beams for the lower entry - other carpenters have erected the posts and beams for the sanctuary level deck

3. Tubing for infloor radiant heat on main and lower levels was installed

4. Carpenters continue framing the downstairs area.