1) Lower level (retail) : Floor was insulated prior to steel placement and pouring of concrete on the floor.
2) The main water meters were hooked up to the building, other utilities will be hooked up this week which means the sewer lines will be tied into the building.
3) Clay Colley is going to pick up beams and posts from Bruce Sargent to be milled by George McKinley who has been working diligently to purchase FSC certified sustainable wood for the building. This is an integral part of our green building effort. These beams and posts will be used to for one of the porches that will be constructed in the next two or three weeks.
4) Interior wall framing will begin shortly in the lower level (retail space).